Everett's Light Rail Timeline, Station by Station and Year by Year

November 19, 2026

If the Sound Transit board picks the option labeled EVT-2C, Everett's northern light rail terminal will be an elevated station near 32nd Street along McDougall Avenue, with its canopy about 55 feet above the ground. If it picks EVT-3D, the station moves north, near Pacific and Hewitt avenues. Both are preferred alternatives in the Everett Link Extension Draft Environmental Impact Statement that Sound Transit published in September 2026. The same document forecasts about 10,700 daily boardings at that station. Trains are scheduled to reach it in 2041.

A buyer comparing Everett neighborhoods this winter would wait a long time for that train. Light rail will change Everett's neighborhoods sooner than that, though. On the Lynnwood Link line, rezoning and apartment construction came years before the trains did. In Everett, the matching decisions fall between early 2027 and 2031: which corners get stations, who runs the buses, and how often the buses come.

Early 2027: the board picks the station sites

The Draft EIS covers 16 miles and studies 17 route options and 18 possible station sites across eight segments. Public comment closed November 2. According to the Everett Link project page, the board is expected to identify or confirm its preferred alternatives in early 2027, and the Final EIS is expected in late 2027 or early 2028.

Parts of the Everett map already have a preferred option. The SW Everett Industrial Center station's preferred site is south of SR 526 near W Casino Road, west of Seaway Boulevard. That puts it in the Paine Field and Boeing employment area, not at the airport terminal. Through the Broadway stretch, the preferred route follows I-5 with no station. Downtown has the two Everett Station options described above.

Three Everett-area stations have no preferred option yet:

  • Mariner: the station could go near 8th Avenue W at 128th Street SW or at the existing Mariner Park-and-Ride. The area is unincorporated Snohomish County, even though many addresses there say Everett.
  • SR 99/Airport Road: this station is provisional, and Sound Transit has no construction funding for it.
  • SR 526/Evergreen: this station in the Casino Road neighborhood could go north of SR 526 near Evergreen Way, north of Casino Road near SR 526, or on E Casino Road east of Evergreen Way.

The Everett Herald reported in September that Mayor Cassie Franklin plans to make community feedback on the SR 526/Evergreen station's location a major focus. In the same article, Lynnwood City Council member and Sound Transit board member David Parshall said the board was looking for feedback from people along the route about what matters to them locally.

If you're house hunting near Casino Road or 128th Street SW this season, the station closest to you could still end up on any of several corners. The board's choice of preferred alternatives in early 2027 is the next step toward a final site.

April 1, 2027: Everett's buses become Community Transit's

The bus system is changing sooner than the rail line. On November 6, 2026, the City of Everett announced that the Everett City Council and the Community Transit Board had both voted unanimously to merge Everett Transit into Community Transit. Community Transit takes over transit operations in Everett on April 1, 2027. Public input on the combined network starts in January 2027, and current Everett routes and schedules will stay mostly the same until the expansion begins.

The city's announcement also says Community Transit's 1.2% transit sales tax will replace Everett's 0.6% rate inside the city on April 1, 2027. The city puts the difference at 6 cents on a $10 taxable purchase.

2028 to 2031: more frequent buses

The agreement between the city and Community Transit includes specific targets. Service expansion starts in 2028. By 2031, transit service in Everett is set to grow by 50%, with more frequent buses and earlier morning and later evening service. An on-demand Zip Shuttle zone is planned for Everett by spring 2028. City Council Vice President Paula Rhyne linked the new bus network to Sound Transit's extension of light rail to Everett.

The bus rapid transit map is growing on the same schedule. Today, according to Community Transit, Swift Blue connects Everett Station with Shoreline North/185th and meets the Swift Green line at Highway 99 and Airport Road. Swift Green runs from Seaway Transit Center near Boeing to Canyon Park in Bothell. Swift buses run every 10 minutes on weekdays and every 15 to 20 minutes on evenings and weekends. The planned Swift Gold line is a 15-mile route linking Everett, Marysville and Arlington through downtown Everett to Everett Station, with service projected to begin in 2031.

So the corner of Highway 99 and Airport Road already has two Swift lines crossing, while its light rail station has no construction funding. Near SW Everett Industrial Center, Swift Green already reaches Seaway Transit Center, a decade before phase 1 of the rail line is scheduled to open.

What happened around Lynnwood Link before August 2024

Sound Transit opened light rail to Lynnwood on August 30, 2024. That line is the closest local example of how station areas change, and most of the change happened before the trains arrived.

Mountlake Terrace updated its Town Center zoning in 2019 to allow buildings up to 12 stories near the future station. Construction on Terrace Station, a three-phase mixed-use project with 636 homes, began in 2018. A late-August 2024 count by The Urbanist found 873 homes completed in Mountlake Terrace's station area since 2019, 425 under construction and 506 in planning or permitting. Shoreline adopted its station-area plans in 2015 and 2016, eight or nine years before opening day. By August 2024, about 600 homes had been built in the Shoreline North/185th station area since 2019, and 767 more were under construction.

Lynnwood City Center had the busiest station on the extension, and some of its biggest projects were still years away when trains arrived. Northline Village's development agreement was approved in December 2019. In January 2026, Lynnwood's new mayor still described it as a future development, according to the Everett Herald. The Lynnwood Times reported in March 2026 that The District's master plan includes 400 housing units, with groundbreaking possible by 2028 and completion targeted for 2032. A Seattle Transit Blog analysis of Sound Transit data estimated about 4,500 average weekday boardings at Lynnwood City Center in May 2025, compared with about 1,500 at Mountlake Terrace and 1,200 at Shoreline North/185th.

Along that line, the zoning decisions set the pace of change near the stations more than the opening date did. Everett has already taken some of those steps. The City Council approved the Everett 2044 comprehensive plan update in 2025, the Herald reports. The city's 2026 budget amendment set aside $50,000 for outreach on a Casino Road subarea plan in 2026 and 2027. Downtown, the 2020 Metro Everett Subarea Plan already called for a combined light rail and bus hub with transit-oriented development around Everett Station.

2034 to 2046: the trains come last

The first major structure on the line won't carry passengers. OMF North, a maintenance and storage yard for more than 150 light rail vehicles, needs 80 to 100 acres and is scheduled to open in 2034, the Herald reported. Its site is one of the choices still open in the Draft EIS.

Passenger service would open in two phases: from Lynnwood City Center to SW Everett Industrial Center in 2037, then to Everett Station in 2041. Parking at the Mariner and Everett Station stations is assumed for 2046. That schedule held through the Sound Transit board's May 28, 2026 vote on Resolution R2026-11, which updated the voter-approved ST3 plan to fit the agency's available funding. The resolution lists phase 1 at $6.1 billion and phase 2 at $3.4 billion. According to the Herald's report on that vote, no Link stations were removed, station parking garages were deferred, and other ST3 projects elsewhere in the region were delayed or deferred. Sound Transit's own project page calls the schedule a plan, not a guarantee.

Two questions buyers ask about Everett Link

Will there be a park-and-ride at the station near me? The Draft EIS includes a 1,000-car garage at the Everett Station site, in the existing Sound Transit park-and-ride lot near Pacific Avenue. It assumes that garage, along with parking at Mariner, opens in 2046, five years after downtown trains are scheduled to start.

Is the Mariner station in Everett? The Draft EIS places the Mariner station in unincorporated Snohomish County, near 128th Street SW, even though addresses there commonly say Everett.

If you're weighing a home near Casino Road, Mariner, Airport Road or the blocks around Everett Station, the station vote in early 2027 and the bus changes that follow will shape that area well before 2041. Dani Robinett can walk through the Draft EIS options with you for the streets you're considering. Schedule a Consultation to get started.